I've got practically no experience with builders and I'm concerned that the costs for this job are totally over the top. Can anyone help figure out if I'm being taken for a ride?
I've had a nightmare with this job and now, after months dealing with the planning office, I'm desperate to get the first stage of work done so that the main part of the building (oak framed extension to an existing stable block, which is being converted) can be done. I've had a price from the builder to get the work done.
In short we need to reduce oversite, pile drive footings for new extension, build support wall for Oak frame, install beam and block floor, install DPC (gas rated), insulate floor and screed, build a couple of return walls, and install a 5 metre steel. All the drawings have been done and paid for, as has all planning, building control application etc. The total cost (nearly £19000+VAT) seems absurd considering I'd still need to put a roof on and then finish the interior. The oak frame has been paid for already and is sitting in storage waiting to be erected.
The total floor area is about 60m square. Here's a more detailed break down.
Mini Digger, 1 day, reduce oversite down by about 200mm to make way for void under new beam and block floor.
Install 8 telescopic air bricks and 6 perp end ventilators to existing stable block.
Fill top of cavity in existing building (17 linear metres approx) with expanding foam (long story, to prevent possible gas migration up cavity).
Grind out same perimeter to allow installation of Gas rated DPC.
Temporary support of front part of existing building. Possible relocation of supports during construction of footings.
Construction of dwarf walls to support new oak extension, up to DPC (16 linear metres) and construction of some block walls inside existing building to support new beam and block floor. New dwarf wall to include several ventilator bricks (telescopic).
Install beam and block floor. Articulated truck and crane.
Installation of Visqueen gas rated DPC.
Construct two return walls (3 linear metres approx. 2.5 metres high). Smooth rendered to exterior.
Remove props and install new steel (5m).
Screed floor (75mm) and insulate (65mm).
Total cost: £11900+VAT
Part way through this the Piling company will come in to Pile the foundations for the new part of the building and install the ring beam.
Cost for Piling: £7000+VAT
Whilst your there, any ideas for a ball park figure for installing a pitched roof (25m square)?
Thanks!
posted by Cog at 10:23 AM on November 14, 2006